BUILDING A BETTER BEDFORD - 4TH AND LINCOLN INTERSECTION CLOSURE -JULY 25TH, 2019
Thursday, July 25, 2019


BUILDING A BETTER BEDFORD WEEKLY UPDATE - JUNE 20TH, 2019
4TH AND LINCOLN INTERSECTION CLOSURE

 Contact:    Misty Adams

                  Director of Utilities                          

                  (812) 275- 1626

                      madams@bedford.in.us  
                                                                    
www.mybedfordonline.in.us

4TH AND LINCOLN INTERSECTION CLOSURE

The 4th and Lincoln Avenue Intersection project still continues.

4th Street has been re-opened for the time being.  There will be temporary closures in the future during concrete work.

P Street at 4th Street is closed.  Studio M Salon has permission to park on P Street while construction continues on Lincoln Avenue.

Lincoln Avenue is closed from 4th Street up to 2nd Street.  Miller Pipeline is working in the area relocating gas mains and Kings Construction will be working right behind them installing storm sewer.

 We estimate this closure to be up to two months while storm water, water, and sewer work continues. 

All businesses are open during construction.

 4TH STREET MARATHON DAIRYLAND AND STUDIO M PARKING LOTS ARE FOR CUSTOMERS ONLY.  THESE ARE NOT FOR TRAFFIC TO PASS THROUGH.

LARGE TRUCKS AND SEMIS ARE TO USE 5TH STREET.

Proceed with caution around this area with the change in traffic pattern.

Thank You,

Misty Adams